Peikko's first major project in Korea.

 

CGN Company Ltd develops a new biomass power plant in Seosan, about 120 km south from Seoul. Biomass turbine driven compressors with shaft power of 110MW.

Peikko delivered Bolted connections to all the precast in the project's cooling tower building. Peikko's HPKM®/PEC® Column Shoes and HPM®/COPRA® Anchor Bolts were used in the project.

With Peikko systems erection of columns is faster and easier than conventional methods.

 

Informazioni sul progetto

Investitore:
CGN DAESAN POWER Co., Ltd.
Impresa di costruzioni:
HYUNDAI ENGINEERING & CONSTRUCTION
Strutturista:
BORU, INHUS
Prefabbricatore:
TAEHWA Engineering Co., Ltd.
Anno della fornitura:
2019
Fine lavori:
2021